Test Plan Template: Free Example for Website and UAT Testing
Last updated: November 18, 2026
A test plan is the document that says what you will test, how, where, by whom, and what counts as done. For a website release it fits on one or two pages: scope, approach, environments, browsers and devices, entry and exit criteria, roles, schedule, risks, and sign-off. Copy the template below or download it as a PDF.
ISTQB defines a test plan as “documentation that describes test objectives, means and schedule for achieving test coordination.” This guide is for agency project leads, QA testers, and developers who test websites before launch. It gives you a template, a filled-in example for a marketing site, and a version for user acceptance testing (UAT).
What a Test Plan Is, and What It Is Not
The formal standard for test documentation is ISO/IEC/IEEE 29119-3, which replaced IEEE 829. Under IEEE 829, a test plan describes the scope, approach, resources, and schedule of testing, and names the items and features to test, the tasks, who owns each task, and the risks. You do not need the full standard for a website. You need the decisions it asks for, written down before testing starts.
| Document | Answers | Example |
|---|---|---|
| Test plan | What, how, where, who, when, and what counts as done | “Test the 12 pages on four browsers, at three widths, in two rounds.” |
| Test strategy | The general approach a team uses on every project | “We test accessibility to WCAG 2.2 AA on every release.” |
| Test case | The exact steps and expected result for one check | “Submit the contact form empty. Each required field shows an error.” |
| Checklist | A list of things to confirm | A website QA checklist |
| Bug report | What went wrong in one place | A bug report with steps to reproduce |
Test Plan Template
Fill in every section before testing starts. A blank section is a decision someone will make later, under deadline.
| Section | What to write |
|---|---|
| 1. Project and release | The project, the version or release being tested, and who owns the plan. |
| 2. Objective | What this round of testing must show, in one or two sentences. |
| 3. Scope | The pages, flows, and features in scope, and a separate list of what is out of scope. |
| 4. Approach | The kinds of testing: functional, visual and design QA, responsive, accessibility, performance, cross-browser, content, and UAT. |
| 5. Environments and test data | The staging address, test accounts, and any data the tests need. |
| 6. Browsers and devices | Each browser, version, and screen width you will test, so “we tested it” means the same thing to everyone. |
| 7. Entry and exit criteria | What must be true before testing starts, and what must be true for testing to be done. |
| 8. Roles | Who leads testing, who tests, which developer fixes, and who approves for the client. |
| 9. Schedule | Dates for each test round, the fix window between rounds, client UAT, and sign-off. |
| 10. Risks | What could stop testing or delay launch, and what you will do about each. |
| 11. Defect process | Where bugs are reported, the severity levels, and how fixes are checked. |
| 12. Sign-off | Who approves the release, and the date. |
Get the test plan template as a two-page PDF with every section above, ready to fill in for your next release.
Test Plan Example: A 12-Page Marketing Website
Here is the template filled in for a typical agency launch. The values are an example to adapt, not a standard.
| Section | Example |
|---|---|
| Objective | Show that the new site is ready to replace the current one on the launch date. |
| In scope | All 12 pages, the contact and newsletter forms, the booking flow, and the cookie banner. |
| Out of scope | The client’s CRM, which receives form leads but is tested by the client’s own team. |
| Approach | Functional, visual against the approved design, responsive, accessibility, performance, cross-browser, and client UAT. |
| Environment | Staging site behind a password; two test accounts; a test email inbox for form submissions. |
| Browsers and devices | Latest Chrome, Safari, Firefox, and Edge; widths of 360, 390, 768, and 1440 pixels. |
| Accessibility target | WCAG 2.2 level AA. |
| Performance target | The “good” Core Web Vitals thresholds: LCP of 2.5 seconds or less, INP of 200 milliseconds or less, CLS of 0.1 or less. |
| Entry criteria | All pages built on staging, final copy and images in place, forms connected. |
| Exit criteria | No open blocker or major bugs, every in-scope flow passes, and the client approver has signed off UAT. |
| Schedule | Round 1, then two days of fixes, round 2, then three days of client UAT, then sign-off. |
| Risks | Late copy from the client delays round 1; the booking provider’s test mode differs from live. |
UAT Test Plan Template
A user acceptance testing plan has the same bones, but different people and a different question. The testers are the client and their users, not your QA team, and the question is whether the site does what the business needs. Write scenarios instead of step-by-step test cases, and tie each one to an acceptance criterion.
| Section | What changes for UAT |
|---|---|
| Testers | The client’s staff or real users, with the time each person can give. |
| Scenarios | Tasks in the user’s words, such as “Book a consultation for next Tuesday.” |
| Acceptance criteria | What each scenario must achieve to pass. See UAT acceptance criteria. |
| How to report issues | One simple way for non-technical testers to show what went wrong and where. |
| Communication | The invitation, instructions, reminder, and sign-off request. See our UAT email templates. |
| Sign-off | Who signs for the client, and what they are agreeing to. |
For the full process, see our guide to user acceptance testing, and SIT vs UAT for where each kind of testing fits.
How to Write a Test Plan in 6 Steps
- Start from the scope. List the pages and flows the release changes, then write down what you will not test and why.
- Choose the kinds of testing. Most website releases need functional, visual, responsive, accessibility, and cross-browser testing. Add performance and UAT for a launch.
- Name the browsers, devices, and widths. A device list turns “tested on mobile” into something two people mean the same way.
- Write exit criteria you can check. “No open blocker or major bugs” can be checked. “Works well” cannot.
- Plan at least two rounds. Leave time to fix what the first round finds and to test the fixes.
- Agree it with the client. Send the plan to the client approver before testing starts, so the exit criteria are shared.
Common Test Plan Mistakes
- A schedule that assumes everything passes. The UK government’s assurance guidance says test schedules “should not assume success at first pass, and allow time for faults identification and rectification.”
- No out-of-scope list. Without it, every untested page becomes an argument after launch.
- No defect process. Bugs arrive by email, chat, and calls, and some never reach the developer. Agree where bugs go and how severity is set; our glossary covers severity vs priority.
- Testing only one screen width. Layout bugs often appear between the widths a design was drawn at.
- Writing the plan after testing starts. A plan written to describe what already happened cannot catch what was missed.
Where a Tool Helps
A test plan decides what to test. The testing itself produces bugs that need to reach a developer with enough detail to fix them. In OverlayQA, testers and clients pin a comment to the element that is wrong, and it becomes an issue with a screenshot, the page address, browser, and screen size. Accessibility Audit, Auto Review, and Visual Comparison check pages for problems nobody reported, and issues sync both ways with Jira, Linear, and other trackers.
Frequently Asked Questions
What should a test plan include?
Scope and out of scope, the testing approach, environments and test data, browsers and devices, entry and exit criteria, roles, schedule, risks, the defect process, and sign-off.
What is the difference between a test plan and a test strategy?
A test strategy is the general approach a team uses across projects. A test plan applies it to one project or release, with its own scope, dates, and people. In ISO/IEC/IEEE 29119-3, the test plan includes the test strategy for that project.
How long should a test plan be?
For a website release, one or two pages is usually enough. Length matters less than whether every section has an answer before testing starts.
Who writes the test plan?
Usually the test lead or the project lead. The client approver should agree the exit criteria, because they decide when the site is ready.
What are entry and exit criteria?
Entry criteria say what must be true before testing starts, such as final content on staging. Exit criteria say what must be true for testing to be done, such as no open blocker or major bugs.
Is a test plan the same as test cases?
No. The plan decides what to test and when. Test cases give the exact steps and expected result for each check.
What is a UAT test plan?
A test plan for user acceptance testing, where the client or real users check that the site does what the business needs. It lists testers, scenarios, acceptance criteria, how to report issues, and who signs off.